(PORTLAND, OR) -- The
Bonneville Power Administration will begin construction of the Central
Ferry-Lower Monumental Transmission Line Project in May. The new line is
expected to carry over 800 additional megawatts of renewable wind energy,
enough to power about half a million Northwest homes when the wind is blowing.
BPA will hold two “Meet the Builder” open houses in late April.
The 38-mile, 500-kilovolt line in Washington will connect the
new Central Ferry Substation in Garfield County to the existing Lower
Monumental Substation in Walla Walla County. It is expected to be energized in
December 2015.
“Building the right facilities in the right place at the right
time is a key principle of our long-term transmission services planning
process,” said Richard Shaheen, BPA vice president for Engineering and
Technical Services. “Specifically, this project will add critical transmission
grid capacity, support new transmission requests from generators in the Snake
River area and be a welcome boost to local and regional economies.”
Over the past several years, numerous power generation
projects, including large wind projects, have requested interconnection with
the BPA system in the Snake River area. After studying the transmission system
and identifying where capacity is available, BPA determined that there is not
enough available transmission capacity to accommodate the requests. Building
the Central Ferry-Lower Monumental project will allow BPA to meet the requests
for transmission and allow additional power to flow between areas east of the
Cascade Mountains to heavily populated areas in the west.
In August 2011, the Central Ferry-Lower Monumental
Transmission Line Project was put on hold because of uncertainties regarding
the need for the new line. However, in August 2013, BPA notified customers,
landowners and stakeholders that it was moving forward with construction of the
line. Existing customer need coupled with an agreement for Portland General
Electric to acquire Phase 2 of Puget Sound Energy’s Lower Snake River Wind
Project, which PGE renamed the Tucannon River Wind Farm, required construction
activities to begin this spring.
The Tucannon River Wind Farm is a key infrastructure
investment that supports PGE’s balanced energy portfolio. Tucannon River will
help PGE satisfy Oregon’s renewable energy standard, which requires the utility
to supply 15 percent of the electricity its customers use from renewable
resources by 2015 and 25 percent by 2025.
In early 2011, BPA completed an environmental impact statement
and preliminary engineering design for the project. BPA issued a record of
decision to build the line in March 2011. Since then, BPA has conducted
additional environmental review of some access road modifications and a
material yard.
The contractor hired to build the new line is MYR Group, a
leading specialty contractor serving the electrical infrastructure market
throughout the United States. It has the experience and expertise to complete
electrical installations of any type and size. MYR Group’s power line
capabilities include transmission, overhead and underground distribution and
substation projects.
For more information, visit the project website at www.bpa.gov/go/centralferrylomo.
April 22, 20144-7 p.m.
Best Western Plus, 7 E. Oak St., Walla Walla, Wash.
Best Western Plus, 7 E. Oak St., Walla Walla, Wash.
April 23, 2014
4-7 p.m.
Best Western Plus, Dayton Hotel and Suites, 507 E. Main St., Dayton, Wash.